COMMERCIAL:
- Upfront Notice:
- Preliminary Notice:
- Required within 30 days of first providing service or materials to the project.
- Follow-up Notice (if not paid):
- Notice of Intent to File Lien:
- Required at least 20 days before filing a lien statement. A lien must be filed within 120 days after last delivery, so BICA sets the deadline for the Intent to File Lien at 100 days of last delivery.
- This notice is available on the BICA member portal.
RESIDENTIAL:
- Same handlings as for Commercial jobs. jobs
PUBLIC:
- Upfront Notice:
- Notice to Contractor: (Notice of Claimants Right to Protection Under Payment Bond or Guarantee)
- Required within 60 days of first delivery.
- Follow-up Notice: There is no statutory follow-up notice.